KSE Altitude Sports Radio
35 ICC-approved 3-inch helical piles, installed in less than four days, to support a new mezzanine inside an existing building for Kroenke Sports & Entertainment.
KSE Altitude Sports Radio
Kroenke Sports & Entertainment remodeled space inside an existing building for its radio studios and needed helical piles to support a new mezzanine.
Working for Saunders Construction on a tight schedule, Park Range installed 35 ICC-approved 3-inch helical piles in less than four days, meeting the customer's critical path. Existing utilities required minor design changes.
Before production piles went in, our crew installed and performed a verification compression load test per ASTM to confirm the design and depth requirements.
Scope of work
- 35 ICC-approved 3-inch helical piles
- Installed inside an existing building in under 4 days
- Verification compression load test per ASTM
- Design adjusted around existing utilities